CG Living is an off-plan project by CG in Dubai Islands, with 116 homes on 17 floors. DLD’s last inspection, on 26 Oct 2026, found it 2% built.
- Built
- 2%
- Handover
- Q2 2028
- Sales in 12 months
- No sales
- Homes
- 116
Progress
2%built
- Q2 2025Building started
- Oct 2026Last inspection · 2%
- Q2 2028Planned handover
Location
Drive times
Dubai Islands Beach, the nearest beach, is 0.0 km away.
Rated schools
- ELITE ENGLISH SCHOOLIndian · Acceptable4.1 kmaway
- Sabari Indian SchoolIndian · Good4.2 kmaway
Getting around
- Gold SouqGreen Line2.7 kmaway
- Dubai InternationalDXB8.3 kmaway
- Al JaddafHigh-speed rail · planned9.0 kmaway
- MeydanEtihad Rail · planned16 kmaway
Developer
CG
- 1 being built, on time
- Escrow bank
- United Bank Limited
- Legal name
- C G Gulf Real Estate Development L.L.C
More questions about CG Living
Q2 2028, the planned date in DLD’s register.
It is not past its planned date. It was 2% built at DLD’s last inspection on 26 Oct 2026, with handover planned in 19 months.
About AED 110k a year for a 1-bed and AED 118k for a 2-bed in Dubai Islands, a gross yield of about 3.4% Estimate.
Of CG’s 1 projects on DLD’s record, 0 are finished. Of the 1 being built, none is past its planned date.
In Dubai Islands. Gold Souq Metro station on the Green Line is 2.7 km away.
More nearby
Off-plan nearby
- Isla Residences by Chaimaa HoldingNo sales0% built · Planned Q1 2028
- Beach Walk Grand by ImtiazFrom AED 3.68M68% built · Planned Q4 2026
- MareaFrom AED 3.27M5% built · Planned Q2 2027
- Treppan Serenique ResidencesFrom AED 3.25M5% built · Planned Q4 2027
- Villa Del Divos ResidencesFrom AED 5.3M52% built · Planned Q2 2027
- Edgewater Residences 2From AED 2.06M55% built · Past planned date