Haven by Aldar 3
Dubai Land Residence ComplexAldar
Haven by Aldar 3 is an off-plan project by Aldar in Dubai Land Residence Complex, with 292 homes on 3 floors. DLD’s last inspection, on 26 Oct 2026, found it 58% built.
- Built
- 58%
- Handover
- Q1 2028
- Sales in 12 months
- 22
- Homes
- 292
Progress
- Q2 2024Building started
- Oct 2026Last inspection · 58%
- Q1 2028Planned handover
Prices
Typical price by size
| Size | Typical price | AED/sq ft | Sales |
|---|---|---|---|
| 3 beds | AED 3.11M1,808 sq ft | 1,686 | 16 |
| 4+ beds | AED 4.08M2,800 sq ft | 1,403 | 6 |
Latest sales
Newest first| Date | Size | Sq ft | AED/sq ft | Price |
|---|---|---|---|---|
| Oct 2026 · 1 sale | ||||
| 15 Oct 2026 | 3 beds | 1,808 | 1,726 | AED 3.12M |
| Sep 2026 · 1 sale | ||||
| 29 Sep 2026 | 3 beds | 1,808 | 1,604 | AED 2.9M |
| Jul 2026 · 1 sale | ||||
| 13 Jul 2026 | 3 beds | 1,808 | 1,618 | AED 2.93M |
| Jun 2026 · 1 sale | ||||
| 2 Jun 2026 | 3 beds | 1,808 | 1,576 | AED 2.85M |
| May 2026 · 2 sales | ||||
| 19 May 2026 | 4+ beds | 2,713 | 1,438 | AED 3.9M |
| 6 May 2026 | 4+ beds | 2,713 | 1,520 | AED 4.13M |
| Apr 2026 · 1 sale | ||||
| 14 Apr 2026 | 3 beds | 1,808 | 1,814 | AED 3.28M |
| Mar 2026 · 1 sale | ||||
| 2 Mar 2026 | 4+ beds | 3,243 | 1,295 | AED 4.2M |
| Feb 2026 · 6 sales | ||||
| 24 Feb 2026 | 3 beds | 1,869 | 1,685 | AED 3.15M |
| 18 Feb 2026 | 4+ beds | 2,886 | 1,369 | AED 3.95M |
| 16 Feb 2026 | 3 beds | 1,981 | 1,666 | AED 3.3M |
| 12 Feb 2026 | 3 beds | 1,808 | 1,770 | AED 3.2M |
| 9 Feb 2026 | 3 beds | 1,808 | 1,531 | AED 2.77M |
| 2 Feb 2026 | 3 beds | 1,861 | 1,720 | AED 3.2M |
| Jan 2026 · 1 sale | ||||
| 19 Jan 2026 | 4+ beds | 3,171 | 1,293 | AED 4.1M |
| Dec 2025 · 5 sales | ||||
| 30 Dec 2025 | 3 beds | 1,808 | 1,715 | AED 3.1M |
| 29 Dec 2025 | 4+ beds | 2,713 | 1,493 | AED 4.05M |
| 25 Dec 2025 | 3 beds | 1,798 | 1,724 | AED 3.1M |
| 15 Dec 2025 | 3 beds | 1,928 | 1,587 | AED 3.06M |
| 1 Dec 2025 | 3 beds | 1,922 | 1,621 | AED 3.12M |
| Nov 2025 · 2 sales | ||||
| 24 Nov 2025 | 3 beds | 1,808 | 1,728 | AED 3.13M |
| 3 Nov 2025 | 3 beds | 1,808 | 1,687 | AED 3.05M |
Location
Drive times
- Downtown Dubai28min
- Dubai Airport (DXB)29min
- Dubai Marina38min
By car. Jumeirah Open Beach, the nearest beach, is 18.8 km away.
Rated schools
- GEMS Wellington Academy -FzeUK · Very good4.1 kmaway
Getting around
- Academic CityBlue Line · opens 20294.0 kmaway
- MeydanEtihad Rail · planned11 kmaway
- CreekGreen Line15 kmaway
- Al JaddafHigh-speed rail · planned16 kmaway
- Dubai InternationalDXB19 kmaway
Area guideDubai Land Residence ComplexFinished homesAED 841/sq ft1-bed rentAED 56k/yrGross yieldEstimate8.4%Developer
- 15 being built, on time
- Escrow bank
- First Abu Dhabi Bank
- Legal name
- Aurora Spv 1 L.L.C
Also being built by Aldar
| Project | Handover | Built |
|---|---|---|
| Haven By Aldar 1Dubai Land Residence Complex | Q4 2027Being built | 44% |
| Athlon BY AL Dar 1Dubai Land Residence Complex | Q2 2028Being built | 18% |
| Verdes by Haven 1Dubai Land Residence Complex | Q2 2028Being built | 13% |
| Verdes by Haven 2Dubai Land Residence Complex | Q2 2028Being built | 27% |
| Athlon BY AL Dar 2Dubai Land Residence Complex | Q3 2028Being built | 12% |
More questions about Haven by Aldar 3
From AED 3.08M for a 1,808 sq ft 3-bed, the lowest typical price paid in the 12 months. 4+ bed flats sell for about AED 4.08M.
Q1 2028, the planned date in DLD’s register.
It is not past its planned date. It was 58% built at DLD’s last inspection on 26 Oct 2026, with handover planned in 16 months.
About AED 100k a year for a 3-bed in Dubai Land Residence Complex, a gross yield of about 8.4% Estimate.
Of Aldar’s 15 projects on DLD’s record, 0 are finished. Of the 15 being built, none is past its planned date.
In Dubai Land Residence Complex, 28 minutes by car to Downtown Dubai and 29 to Dubai Airport (DXB). Creek Metro station on the Green Line is 15 km away.
More nearby
Off-plan nearby
- Verdes by Haven 1From AED 1.21M13% built · Planned Q2 2028
- Verdes by Haven 2No sales27% built · Planned Q2 2028
- Haven by Aldar 2From AED 3.09M40% built · Handover not on record
- Haven by Aldar 1From AED 3.08M44% built · Planned Q4 2027
- Forest City Tower 2From AED 652k1% built · Planned Q2 2027
- AG 9INEFrom AED 488k38% built · Handover not on record