Ldwi Hotel is an off-plan project by Heart of Europe in The World, with 86 homes on 7 floors. DLD’s last inspection found it 27% built.

Built
27%
Handover
Q4 2027
Sales in 12 months
No sales
Homes
86

Progress

27%built
  1. Q3 2023Building started
  2. Jun 2026Last inspection · 27%
  3. Q4 2027Planned handover

DLD updates % built after each inspection, so work on site can be further along than this figure.

Location

Developer

Heart of Europe

  • 1 not started
Escrow bank
Abu Dhabi Commercial Bank
Legal name
London D W I Real Estate Development L.L.C
Questions

More questions about Ldwi Hotel

Q4 2027, the planned date in DLD’s register.

It is not past its planned date. It was 27% built at DLD’s last inspection, with handover planned in 13 months.

Of Heart of Europe’s 1 projects on DLD’s record, 0 are finished.