Maserati Island by Samana
The WorldSamana
Maserati Island by Samana is an off-plan project by Samana in The World, with 232 homes on 4 floors. DLD’s last inspection, on 16 Jul 2026, found it 0% built.
- Built
- 0%
- Handover
- Q4 2030
- Sales in 12 months
- No sales
- Homes
- 232
Progress
- Jul 2026Last inspection · 0%
- Q3 2026Building started
- Q4 2030Planned handover
DLD updates % built after each inspection, so work on site can be further along than this figure.
Homes
232 homes by size
- Studio37%86 homes · 302–532 sq ft · 13 layouts
- 1 bed47%108 homes · 581–816 sq ft · 16 layouts
- 2 beds10%24 homes · 1,074–1,824 sq ft · 5 layouts
- 3 beds3%8 homes · 1,563–2,966 sq ft · 3 layouts
- 4 beds3%6 homes · 2,822–4,417 sq ft · 3 layouts
Location
Drive times
Jumeirah Open Beach, the nearest beach, is 7.4 km away.
Rated schools
No rated schools within 5 km
Getting around
- ONPASSIVERed Line9.8 kmaway
- MeydanEtihad Rail · planned16 kmaway
- Al JaddafHigh-speed rail · planned17 kmaway
- Dubai InternationalDXB21 kmaway
Developer
- 6 finished
- 41 being built, on time
- 8 past their planned date
- 2 not started
- Escrow bank
- Not on record
- Legal name
- Samana Lux Real Estate Developments L.L.C
Also being built by Samana
| Project | Handover | Built |
|---|---|---|
| Samana MykonosDubai Studio City | Q2 2025Past planned date | 91% |
| Samana WavesJVC | Q4 2025Past planned date | 91% |
| Miami BY SDJumeirah Village Triangle | Q4 2025Past planned date | 71% |
| Samana Waves 2JVC | Q1 2026Past planned date | 52% |
| Samana Mykonos SignatureArjan | Q2 2026Past planned date | 86% |
More questions about Maserati Island by Samana
Q4 2030, the planned date in DLD’s register.
It is not past its planned date. It was 0% built at DLD’s last inspection on 16 Jul 2026, with handover planned in 4 years.
232 homes on 4 floors: 86 studios of 302–532 sq ft, 108 1-bed flats of 581–816 sq ft, 24 2-bed flats of 1,074–1,824 sq ft, 8 3-bed flats of 1,563–2,966 sq ft and 6 4+ bed flats of 2,822–4,417 sq ft.
Of Samana’s 57 projects on DLD’s record, 6 are finished. Of the 49 being built, 8 are past their planned date.
In The World. ONPASSIVE Metro station on the Red Line is 9.8 km away.