Skip to content

Saddlewood Park

MeydanMAK

FromAED 1.73M1 bed · 770 sq ft

Saddlewood Park is an off-plan project by MAK in Meydan, with 61 homes on 4 floors. DLD’s last inspection, on 26 Oct 2026, found it 12% built.

Built
12%
Handover
Q3 2027
Sales in 12 months
18
Homes
61

Progress

12%built
  1. Q4 2025Building started
  2. Oct 2026Last inspection · 12%
  3. Q3 2027Planned handover

Prices

Price per sq ft

2,169 AED/sq ft18 sales in 12 months

Typical price by size

1 bed
AED 1.73M770 sq ft · 2,239 AED/sq ft · 7 sales
2 beds
AED 2.6M1,189 sq ft · 2,187 AED/sq ft · 9 sales
3 beds
Not enough sales2 sales

Against 14 Meydan off-plan projects with 10 or more sales

  • Lowest1,645AED/sq ft
  • Saddlewood Park2,169AED/sq ft
  • Typical2,270AED/sq ft
  • Highest3,670AED/sq ft

4th lowest of 14 · AED per sq ft in 12 months

Latest sales

Plus 1 newer sale, newest first
18 off-plan sales · Nov 2025 – Oct 2026, plus 1 newer sale · newest first
DateSizeSq ftAED/sq ftPrice
Nov 2026
16 Nov 20262 beds New1,3041,833AED 2.39M
Oct 2026 · 1 sale
20 Oct 20263 beds2,5551,761AED 4.5M
Jun 2026 · 2 sales
17 Jun 20261 bed8092,043AED 1.65M
11 Jun 20263 beds2,4641,664AED 4.1M
May 2026 · 2 sales
19 May 20261 bed7702,240AED 1.73M
19 May 20261 bed7272,373AED 1.73M
Apr 2026 · 1 sale
20 Apr 20262 beds1,1022,359AED 2.6M
Mar 2026 · 2 sales
26 Mar 20261 bed7672,152AED 1.65M
4 Mar 20261 bed7902,538AED 2.01M
Jan 2026 · 2 sales
28 Jan 20262 beds1,1892,187AED 2.6M
22 Jan 20262 beds1,5311,927AED 2.95M
Dec 2025 · 6 sales
17 Dec 20251 bed7902,342AED 1.85M
17 Dec 20252 beds1,3612,131AED 2.9M
15 Dec 20252 beds1,1732,195AED 2.58M
15 Dec 20252 beds1,1292,347AED 2.65M
15 Dec 20252 beds1,1772,251AED 2.65M
8 Dec 20252 beds1,3491,809AED 2.44M
Nov 2025 · 2 sales
14 Nov 20251 bed7602,069AED 1.57M
13 Nov 20252 beds1,3631,862AED 2.54M

Homes

61 homes by size

  • 1 bed30%18 homes · 716–809 sq ft · 6 layouts
  • 2 beds62%38 homes · 1,074–2,568 sq ft · 16 layouts
  • 3 beds8%5 homes · 2,111–2,643 sq ft · 4 layouts

Location

Drive times

  • Downtown Dubai20min
  • Dubai Airport (DXB)26min
  • Dubai Marina32min

By car. Mercato Beach, the nearest beach, is 8.1 km away.

Rated schools

  • Hartland International School - FZUK · Very good1.5 kmaway

Getting around

  • MeydanGold Line · opens 203213 minwalk
  • MeydanEtihad Rail · planned13 minwalk
  • Business BayRed Line5.3 kmaway
  • Al JaddafHigh-speed rail · planned7.3 kmaway
  • Dubai InternationalDXB11 kmaway
Area guideMeydanFinished homesAED 1,596/sq ft1-bed rentAED 78k/yrGross yieldEstimate5.8%

Developer

  • 2 being built, on time
Escrow bank
Sharjah Islamic Bank
Legal name
MAK Developers L.L.C

Also being built by MAK

MAK’s other projects
ProjectHandoverBuilt
MAK I'Sola BellaJVCQ3 2027Being built27%
All 2 MAK projects
Questions

More questions about Saddlewood Park

From AED 1.73M for a 770 sq ft 1-bed, the lowest typical price paid in the 12 months. 2-bed flats sell for about AED 2.6M.

Q3 2027, the planned date in DLD’s register.

It is not past its planned date. It was 12% built at DLD’s last inspection on 26 Oct 2026, with handover planned in 10 months.

61 homes on 4 floors: 18 1-bed flats of 716–809 sq ft, 38 2-bed flats of 1,074–2,568 sq ft and 5 3-bed flats of 2,111–2,643 sq ft.

About AED 78k a year for a 1-bed, AED 125k for a 2-bed and AED 170k for a 3-bed in Meydan, a gross yield of about 5.8% Estimate.

Of MAK’s 2 projects on DLD’s record, 0 are finished. Of the 2 being built, none is past its planned date.

In Meydan, 20 minutes by car to Downtown Dubai and 26 to Dubai Airport (DXB). Business Bay Metro station on the Red Line is 5.3 km away.

More nearby

How the numbers work

FromAED 1.73MSee it on the map