Elwood Estates

The ValleySobha

Elwood Estates is an off-plan project by Sobha in The Valley. DLD’s last inspection, on 26 Oct 2026, found it 14% built.

Built
14%
Handover
Q2 2028
Sales in 12 months
No sales
Homes
Not on record

Progress

14%built
  1. Q3 2025Building started
  2. Oct 2026Last inspection · 14%
  3. Q2 2028Planned handover

Location

Drive times

  • Downtown Dubai38min
  • Dubai Marina44min

By car. Jumeirah Open Beach, the nearest beach, is 28.4 km away.

Rated schools

No rated schools within 5 km

Getting around

  • Academic CityBlue Line · opens 202910 kmaway
  • MeydanEtihad Rail · planned20 kmaway
  • CentrepointRed Line23 kmaway
  • Al JaddafHigh-speed rail · planned25 kmaway
  • Dubai InternationalDXB26 kmaway
Area guideThe ValleyFinished homesNot enough sales1-bed rentNot enough rents

Developer

  • 20 finished
  • 24 being built, on time
  • 1 not started
Escrow bank
First Abu Dhabi Bank
Legal name
Sobha L.L.C

Also being built by Sobha

Sobha’s other projects
ProjectHandoverBuilt
Verde by SobhaJLTQ2 2027Being built85%
Sobha EstatesBu KadraQ4 2027Being built68%
Sobha Seahaven Tower ADubai MarinaQ2 2028Being built37%
Sobha Seahaven Tower B & CDubai MarinaQ4 2028Being built40%
Sobha OrbisMotor CityQ4 2028Being built18%
All 45 Sobha projects
Questions

More questions about Elwood Estates

Q2 2028, the planned date in DLD’s register.

It is not past its planned date. It was 14% built at DLD’s last inspection on 26 Oct 2026, with handover planned in 19 months.

Of Sobha’s 45 projects on DLD’s record, 20 are finished. Of the 24 being built, none is past its planned date.

In The Valley, 38 minutes by car to Downtown Dubai and 44 to Dubai Marina. Centrepoint Metro station on the Red Line is 23 km away.