Faro 2 The Heights
The Heights Country ClubEmaar
Faro 2 The Heights is an off-plan project by Emaar in The Heights Country Club, with 200 homes on 2 floors. DLD’s last inspection, on 26 Oct 2026, found it 0% built.
- Built
- 0%
- Handover
- Q2 2030
- Sales in 12 months
- No sales
- Homes
- 200
Progress
0%built
- Q3 2026Building started
- Oct 2026Last inspection · 0%
- Q2 2030Planned handover
Location
Drive times
- Downtown Dubai41min
- Dubai Marina39min
By car. JBR Beach, the nearest beach, is 17.6 km away.
Rated schools
No rated schools within 5 km
Getting around
- Dubai Production CityGold Line · opens 20329.7 kmaway
- Expo 2020Red Line9.7 kmaway
- Al YalayisEtihad Rail10.0 kmaway
- Al Maktoum AirportHigh-speed rail · planned11 kmaway
- Al Maktoum InternationalDWC11 kmaway
Developer
- 193 finished
- 139 being built, on time
- 3 past their planned date
- Escrow bank
- Not on record
- Legal name
- Emaar Development P.J.S.C.
Also being built by Emaar
| Project | Handover | Built |
|---|---|---|
| MaysanTown Square | Q3 2016Past planned date | 37% |
| Teema 1 & Teema 2Al Yalayis 4 | Q3 2016Past planned date | 9% |
| Ocean StarDubai Maritime City | Q3 2025Past planned date | 30% |
| SeascapeDubai Maritime City | Q4 2026Being built | 79% |
| The St. Regis Residences, Downtown DubaiDowntown Dubai | Q4 2026Being built | 76% |
More questions about Faro 2 The Heights
Q2 2030, the planned date in DLD’s register.
It is not past its planned date. It was 0% built at DLD’s last inspection on 26 Oct 2026, with handover planned in 4 years.
Of Emaar’s 335 projects on DLD’s record, 193 are finished. Of the 142 being built, 3 are past their planned date.
In The Heights Country Club, 41 minutes by car to Downtown Dubai and 39 to Dubai Marina. Expo 2020 Metro station on the Red Line is 9.7 km away.
