The Valley - Avena 2
The ValleyEmaar
The Valley - Avena 2 is an off-plan project by Emaar in The Valley, with 332 homes on 3 floors. DLD’s last inspection, on 26 Oct 2026, found it 43% built.
- Built
- 43%
- Handover
- Q3 2028
- Sales in 12 months
- 7
- Homes
- 332
Progress
43%built
- Q3 2024Building started
- Oct 2026Last inspection · 43%
- Q3 2028Planned handover
Prices
Typical price by size
| Size | Typical price | AED/sq ft | Sales |
|---|---|---|---|
| 4+ beds | AED 4.44M3,327 sq ft | 1,269 | 7 |
Latest sales
Newest first| Date | Size | Sq ft | AED/sq ft | Price |
|---|---|---|---|---|
| Oct 2026 · 1 sale | ||||
| 19 Oct 2026 | 4+ beds | 4,402 | 1,040 | AED 4.58M |
| Aug 2026 · 1 sale | ||||
| 10 Aug 2026 | 4+ beds | 3,304 | 1,329 | AED 4.39M |
| Jun 2026 · 1 sale | ||||
| 29 Jun 2026 | 4+ beds | 3,233 | 1,175 | AED 3.8M |
| Dec 2025 · 2 sales | ||||
| 25 Dec 2025 | 4+ beds | 5,230 | 908 | AED 4.75M |
| 4 Dec 2025 | 4+ beds | 3,504 | 1,269 | AED 4.44M |
| Nov 2025 · 2 sales | ||||
| 19 Nov 2025 | 4+ beds | 3,295 | 1,345 | AED 4.43M |
| 10 Nov 2025 | 4+ beds | 3,327 | 1,478 | AED 4.92M |
Location
Drive times
- Downtown Dubai38min
- Dubai Marina44min
By car. Kite Beach, the nearest beach, is 29.9 km away.
Rated schools
No rated schools within 5 km
Getting around
- Academic CityBlue Line · opens 202912 kmaway
- MeydanEtihad Rail · planned22 kmaway
- CentrepointRed Line26 kmaway
- Al JaddafHigh-speed rail · planned27 kmaway
- Dubai InternationalDXB29 kmaway
Area guideThe ValleyFinished homesNot enough sales1-bed rentNot enough rentsDeveloper
- 193 finished
- 139 being built, on time
- 3 past their planned date
- Escrow bank
- Emirates NBD Bank
- Legal name
- Emaar Development P.J.S.C.
Also being built by Emaar
| Project | Handover | Built |
|---|---|---|
| MaysanTown Square | Q3 2016Past planned date | 37% |
| Teema 1 & Teema 2Al Yalayis 4 | Q3 2016Past planned date | 9% |
| Ocean StarDubai Maritime City | Q3 2025Past planned date | 30% |
| SeascapeDubai Maritime City | Q4 2026Being built | 79% |
| The St. Regis Residences, Downtown DubaiDowntown Dubai | Q4 2026Being built | 76% |
More questions about The Valley - Avena 2
Q3 2028, the planned date in DLD’s register.
It is not past its planned date. It was 43% built at DLD’s last inspection on 26 Oct 2026, with handover planned in 22 months.
Of Emaar’s 335 projects on DLD’s record, 193 are finished. Of the 142 being built, 3 are past their planned date.
In The Valley, 38 minutes by car to Downtown Dubai and 44 to Dubai Marina. Centrepoint Metro station on the Red Line is 26 km away.
More nearby
Off-plan nearby
- The Valley - RiveraNo sales4% built · Planned Q4 2028
- The Valley - AvenaNo sales24% built · Planned Q2 2028
- The Valley - AlanaNo sales82% built · Handover not on record
- The Valley - VeneraFrom AED 2.9M52% built · Planned Q3 2028
- The Valley - VeloraFrom AED 2.79M50% built · Planned Q3 2028
- The Valley - VinderaFrom AED 3.13M2% built · Planned Q4 2028