Verdana (Phase 1)

Dubai Investments Park 1Reportage

Verdana (Phase 1) is an off-plan project by Reportage in Dubai Investments Park 1, with 178 homes on 4 floors. DLD’s last inspection, on 26 Oct 2026, found it 95% built.

Built
95%
Handover
Q4 2025
Sales in 12 months
No sales
Homes
178

Progress

95%built
  1. Q3 2022Building started
  2. Q4 2025Planned handover · passed
  3. Oct 2026Last inspection · 95%
11 months past the planned date

Location

Drive times

  • Downtown Dubai37min
  • Dubai Airport (DXB)45min
  • Dubai Marina26min

By car.

Area guideDubai Investments Park 1Finished homesNot enough sales1-bed rentAED 65k/yr

Developer

  • 1 finished
  • 12 being built, on time
  • 4 past their planned date
  • 9 not started
Escrow bank
Arab Bank for Investment & Foreign Trade Almasref
Legal name
Reportage Prime Properties L.L.C

Also being built by Reportage

Reportage’s other projects
ProjectHandoverBuilt
Verdana ResidenceDubai Investment Park FirstQ4 2025Past planned date96%
Verdana(Phase 2)Dubai Investment Park FirstQ4 2025Past planned date94%
Verdana Residence 2Dubai Investment Park FirstQ2 2026Past planned date20%
BiancaLiwanQ4 2026Being built56%
Verdana 3Dubai Investment Park FirstQ3 2027Being built0%
All 26 Reportage projects
Questions

More questions about Verdana (Phase 1)

Q4 2025, the planned date in DLD’s register.

No. It is 11 months past its planned date, and was 95% built at DLD’s last inspection on 26 Oct 2026.

About AED 31k a year for a studio, AED 65k for a 1-bed, AED 85k for a 2-bed and AED 130k for a 3-bed in Dubai Investments Park 1.

Of Reportage’s 26 projects on DLD’s record, 1 are finished. Of the 16 being built, 4 are past their planned date.

In Dubai Investments Park 1, 37 minutes by car to Downtown Dubai and 45 to Dubai Airport (DXB).