Beachfront Gates 1
Dubai SouthDubai South
Beachfront Gates 1 is an off-plan project by Dubai South in Dubai South, with 70 homes on 6 floors. DLD’s last inspection, on 26 Oct 2026, found it 36% built.
- Built
- 36%
- Handover
- Q4 2026
- Sales in 12 months
- No sales
- Homes
- 70
Progress
- Q1 2025Building started
- Oct 2026Last inspection · 36%
- Q4 2026Planned handover
Homes
70 homes by size
- 1 bed33%23 homes · 866–1,102 sq ft · 5 layouts
- 2 beds50%35 homes · 1,228–2,788 sq ft · 8 layouts
- 3 beds17%12 homes · 2,057–3,090 sq ft · 3 layouts
Location
Drive times
- Downtown Dubai42min
- Dubai Airport (DXB)47min
- Dubai Marina28min
By car. JBR Beach, the nearest beach, is 18.5 km away.
Rated schools
No rated schools within 5 km
Getting around
- Al Maktoum AirportHigh-speed rail · planned7.7 kmaway
- Al Maktoum InternationalDWC7.7 kmaway
- Expo 2020Red Line8.3 kmaway
- Al YalayisEtihad Rail11 kmaway
Area guideDubai SouthFinished homesAED 1,100/sq ft1-bed rentAED 57k/yrGross yieldEstimate7.4%Developer
- 13 finished
- 15 being built, on time
- 3 past their planned date
- Escrow bank
- Abu Dhabi Commercial Bank
- Legal name
- Dubai South Properties Dwc LLC
Also being built by Dubai South
| Project | Handover | Built |
|---|---|---|
| South LivingDubai South | Q1 2020Past planned date | 89% |
| South Bay 1Dubai South | Q1 2025Past planned date | 94% |
| South Bay 2Dubai South | Q2 2026Past planned date | 94% |
| Beachfront Gates 2Dubai South | Q4 2026Being built | 61% |
| Hayat 3Dubai South | Q2 2028Being built | 4% |
More questions about Beachfront Gates 1
Q4 2026, the planned date in DLD’s register.
It is not past its planned date. It was 36% built at DLD’s last inspection on 26 Oct 2026, with handover planned in 1 month.
70 homes on 6 floors: 23 1-bed flats of 866–1,102 sq ft, 35 2-bed flats of 1,228–2,788 sq ft and 12 3-bed flats of 2,057–3,090 sq ft.
About AED 57k a year for a 1-bed, AED 85k for a 2-bed and AED 120k for a 3-bed in Dubai South, a gross yield of about 7.4% Estimate.
Of Dubai South’s 31 projects on DLD’s record, 13 are finished. Of the 18 being built, 3 are past their planned date.
In Dubai South, 42 minutes by car to Downtown Dubai and 47 to Dubai Airport (DXB). Expo 2020 Metro station on the Red Line is 8.3 km away.
More nearby
Off-plan nearby
- Beachfront Gates 2From AED 1.09M61% built · Planned Q4 2026
- Unique OneNo sales0% built · Planned Q4 2026
- Cresswell PlazaNo sales65% built · Past planned date
- Westar AltairFrom AED 1.03M63% built · Planned Q2 2027
- Lincoln Star Residence IINo sales5% built · Planned Q3 2027
- Casa Aura ResidenceFrom AED 977k6% built · Planned Q3 2027
Finished buildings nearby
Typical next door AED 997/sq ft · 4 buildings within a 10-minute walk
- Kappa Acca 4965AED/sq ftNot enough rents · 10-minute walk
- Kappa Acca 31,063AED/sq ft1-bed rent AED 52k/yr · 10-minute walk
- The Pulse Residence Plaza1,020AED/sq ft1-bed rent AED 55k/yr · 10-minute walk
- The Pulse Boulevard Apartments-C1973AED/sq ft1-bed rent AED 60k/yr · 10-minute walk
- MAG 5 Boulevard1,124AED/sq ft1-bed rent AED 51k/yr
- Celestia1,109AED/sq ft1-bed rent AED 63k/yr
- Majestique Residence 21,318AED/sq ftNot enough rents
- Majestique Residence 11,209AED/sq ft1-bed rent AED 63k/yr