Golf Verge is an off-plan project by Emaar in Dubai South, with 204 homes on 11 floors. DLD’s last inspection, on 26 Oct 2026, found it 4% built.

Built
4%
Handover
Q2 2029
Sales in 12 months
13
Homes
204

Progress

4%built
  1. Apr–Jun 2025Launch sales · 19
  2. Q3 2025Building started
  3. Oct 2026Last inspection · 4%
  4. Q2 2029Planned handover

Prices

Price per sq ft

1,864 AED/sq ft13 sales in 12 months

Typical price by size

2 beds
Not enough sales1 sale

Against 66 Dubai South off-plan projects with 10 or more sales

  • Lowest750AED/sq ft
  • Typical1,580AED/sq ft
  • Golf Verge1,864AED/sq ft
  • Highest2,550AED/sq ft

15th highest of 66 · AED per sq ft in 12 months

Latest sales

Newest first
13 off-plan sales · Nov 2025 – Oct 2026 · newest first
DateSizeSq ftAED/sq ftPrice
Jul 2026 · 3 sales
27 Jul 20262 beds1,3641,734AED 2.36M
20 Jul 20263 beds1,8041,687AED 3.04M
7 Jul 20263 beds1,7731,932AED 3.42M
Apr 2026 · 2 sales
20 Apr 20262 beds1,4721,852AED 2.73M
20 Apr 20262 beds1,5551,776AED 2.76M
Feb 2026 · 2 sales
16 Feb 20261 bed7991,578AED 1.26M
2 Feb 20262 beds1,3171,959AED 2.58M
Jan 2026 · 2 sales
30 Jan 20262 beds1,5611,718AED 2.68M
30 Jan 20262 beds1,3081,959AED 2.56M
Dec 2025 · 2 sales
22 Dec 20253 beds1,6831,945AED 3.27M
8 Dec 20252 beds1,3971,866AED 2.61M
Nov 2025 · 2 sales
19 Nov 20252 beds1,4021,864AED 2.61M
17 Nov 20252 beds1,3171,959AED 2.58M

Homes

204 homes by size

  • 1 bed32%66 homes · 803–1,012 sq ft · 4 layouts
  • 2 beds59%120 homes · 1,310–1,697 sq ft · 8 layouts
  • 3 beds9%18 homes · 1,685–1,781 sq ft · 2 layouts

Location

Drive times

  • Downtown Dubai39min
  • Dubai Airport (DXB)44min
  • Dubai Marina28min

By car.

Area guideDubai SouthFinished homesAED 1,100/sq ft1-bed rentAED 57k/yrGross yieldEstimate7.4%

Developer

  • 193 finished
  • 139 being built, on time
  • 3 past their planned date
Escrow bank
Mashreq Bank
Legal name
Emaar Dubai South Dwc LLC

Also being built by Emaar

Emaar’s other projects
ProjectHandoverBuilt
MaysanTown SquareQ3 2016Past planned date37%
Teema 1 & Teema 2Al Yalayis 4Q3 2016Past planned date9%
Ocean StarDubai Maritime CityQ3 2025Past planned date30%
SeascapeDubai Maritime CityQ4 2026Being built79%
The St. Regis Residences, Downtown DubaiDowntown DubaiQ4 2026Being built76%
All 335 Emaar projects
Questions

More questions about Golf Verge

Q2 2029, the planned date in DLD’s register.

It is not past its planned date. It was 4% built at DLD’s last inspection on 26 Oct 2026, with handover planned in 3 years.

204 homes on 11 floors: 66 1-bed flats of 803–1,012 sq ft, 120 2-bed flats of 1,310–1,697 sq ft and 18 3-bed flats of 1,685–1,781 sq ft.

About AED 57k a year for a 1-bed, AED 85k for a 2-bed and AED 120k for a 3-bed in Dubai South, a gross yield of about 7.4% Estimate.

Of Emaar’s 335 projects on DLD’s record, 193 are finished. Of the 142 being built, 3 are past their planned date.

In Dubai South, 39 minutes by car to Downtown Dubai and 44 to Dubai Airport (DXB).

More nearby