Greenway is an off-plan project by Emaar in Dubai South, with 232 homes on 3 floors. DLD’s last inspection, on 26 Oct 2026, found it 39% built.

Built
39%
Handover
Not on record
Sales in 12 months
6
Homes
232

Progress

39%built
  1. Q4 2024Building started
  2. Oct 2026Last inspection · 39%

Prices

Typical price by size

Typical price by size · Nov 2025 – Oct 2026
SizeTypical priceAED/sq ftSales
3 bedsNot enough sales2
4+ bedsAED 3.93M3,094 sq ft1,1784

Latest sales

Newest first
6 off-plan sales · Nov 2025 – Oct 2026 · newest first
DateSizeSq ftAED/sq ftPrice
Jul 2026 · 1 sale
2 Jul 20264+ beds5,487760AED 4.17M
Jun 2026 · 1 sale
29 Jun 20264+ beds2,9671,062AED 3.15M
Apr 2026 · 1 sale
15 Apr 20264+ beds3,2211,311AED 4.22M
Feb 2026 · 2 sales
12 Feb 20263 beds1,8601,832AED 3.41M
12 Feb 20264+ beds2,8481,294AED 3.69M
Nov 2025 · 1 sale
14 Nov 20253 beds1,8571,807AED 3.36M

Location

Drive times

  • Downtown Dubai39min
  • Dubai Airport (DXB)44min
  • Dubai Marina28min

By car.

Area guideDubai SouthFinished homesAED 1,100/sq ft1-bed rentAED 57k/yrGross yieldEstimate7.4%

Developer

  • 193 finished
  • 139 being built, on time
  • 3 past their planned date
Escrow bank
Dubai Islamic Bank
Legal name
Emaar Dubai South Dwc LLC

Also being built by Emaar

Emaar’s other projects
ProjectHandoverBuilt
MaysanTown SquareQ3 2016Past planned date37%
Teema 1 & Teema 2Al Yalayis 4Q3 2016Past planned date9%
Ocean StarDubai Maritime CityQ3 2025Past planned date30%
SeascapeDubai Maritime CityQ4 2026Being built79%
The St. Regis Residences, Downtown DubaiDowntown DubaiQ4 2026Being built76%
All 335 Emaar projects
Questions

More questions about Greenway

About AED 120k a year for a 3-bed in Dubai South, a gross yield of about 7.4% Estimate.

Of Emaar’s 335 projects on DLD’s record, 193 are finished. Of the 142 being built, 3 are past their planned date.

In Dubai South, 39 minutes by car to Downtown Dubai and 44 to Dubai Airport (DXB).

More nearby