One Mansory

Motor CityAmaal

One Mansory is an off-plan project by Amaal in Motor City. DLD’s last inspection, on 28 Feb 2026, found it 0% built.

Built
0%
Handover
Q2 2029
Sales in 12 months
No sales
Homes
Not on record

Progress

0%built
  1. Feb 2026Last inspection · 0%
  2. Q2 2026Building started
  3. Q2 2029Planned handover

DLD updates % built after each inspection, so work on site can be further along than this figure.

Location

Drive times

  • Downtown Dubai26min
  • Dubai Airport (DXB)33min
  • Dubai Marina24min

By car.

Area guideMotor CityFinished homesAED 1,000/sq ft1-bed rentAED 73k/yrGross yieldEstimate7.6%

Developer

  • 1 being built, on time
  • 1 not started
Escrow bank
Not on record
Legal name
Divine AT 311 Developers L.L.C

Also being built by Amaal

Amaal’s other projects
ProjectHandoverBuilt
AMAAL 8Ras Al Khor Ind. FirstQ4 2028Being built7%
All 2 Amaal projects
Questions

More questions about One Mansory

Q2 2029, the planned date in DLD’s register.

It is not past its planned date. It was 0% built at DLD’s last inspection on 28 Feb 2026, with handover planned in 3 years.

About AED 52k a year for a studio, AED 73k for a 1-bed, AED 118k for a 2-bed and AED 165k for a 3-bed in Motor City, a gross yield of about 7.6% Estimate.

Of Amaal’s 2 projects on DLD’s record, 0 are finished. Of the 1 being built, none is past its planned date.

In Motor City, 26 minutes by car to Downtown Dubai and 33 to Dubai Airport (DXB).