Pier Point 2
Mina RashidEmaar
Pier Point 2 is an off-plan project by Emaar in Mina Rashid, with 121 homes on 10 floors. DLD’s last inspection, on 26 Oct 2026, found it 8% built.
- Built
- 8%
- Handover
- Q4 2028
- Sales in 12 months
- No sales
- Homes
- 121
Progress
- Oct–Dec 2024Launch sales · 103
- Q1 2025Building started
- Oct 2026Last inspection · 8%
- Q4 2028Planned handover
Prices
Price per sq ft
Latest sales
No sales in 12 months, plus 1 newer sale, newest first| Date | Size | Sq ft | AED/sq ft | Price |
|---|---|---|---|---|
| Nov 2026 | ||||
| 13 Nov 2026 | 1 bed New | 804 | 3,172 | AED 2.55M |
Homes
121 homes by size
- 1 bed46%56 homes · 774–810 sq ft · 4 layouts
- 2 beds42%51 homes · 1,213–1,373 sq ft · 5 layouts
- 3 beds12%14 homes · 1,672–2,709 sq ft · 4 layouts
Location
Drive times
- Downtown Dubai19min
- Dubai Airport (DXB)26min
- Dubai Marina32min
By car.
Area guideDubai Maritime CityFinished homesAED 2,151/sq ft1-bed rentAED 75k/yrGross yieldEstimate4.0%Developer
- 193 finished
- 139 being built, on time
- 3 past their planned date
- Escrow bank
- Emirates NBD Bank
- Legal name
- Mina Rashid Properties L.L.C
Also being built by Emaar
| Project | Handover | Built |
|---|---|---|
| MaysanTown Square | Q3 2016Past planned date | 37% |
| Teema 1 & Teema 2Al Yalayis 4 | Q3 2016Past planned date | 9% |
| Ocean StarDubai Maritime City | Q3 2025Past planned date | 30% |
| SeascapeDubai Maritime City | Q4 2026Being built | 79% |
| The St. Regis Residences, Downtown DubaiDowntown Dubai | Q4 2026Being built | 76% |
More questions about Pier Point 2
Q4 2028, the planned date in DLD’s register.
It is not past its planned date. It was 8% built at DLD’s last inspection on 26 Oct 2026, with handover planned in 2 years.
121 homes on 10 floors: 56 1-bed flats of 774–810 sq ft, 51 2-bed flats of 1,213–1,373 sq ft and 14 3-bed flats of 1,672–2,709 sq ft.
About AED 75k a year for a 1-bed, AED 110k for a 2-bed and AED 146k for a 3-bed in Dubai Maritime City, a gross yield of about 4.0% Estimate.
Of Emaar’s 335 projects on DLD’s record, 193 are finished. Of the 142 being built, 3 are past their planned date.
In Mina Rashid, Dubai Maritime City, 19 minutes by car to Downtown Dubai and 26 to Dubai Airport (DXB).
More nearby
Off-plan nearby
- Breez by DanubeFrom AED 1.4M1% built · Planned Q2 2029
- Franck Muller YachtingFrom AED 1.35M0% built · Planned Q3 2028
- Kanyon by BeyondFrom AED 2.58M4% built · Planned Q3 2028
- Chelsea Residences 2 by DAMACFrom AED 2.64M5% built · Planned Q4 2029
- Soulever' by BeyondFrom AED 3.09M2% built · Planned Q4 2028
- AureaFrom AED 2.36M0% built · Planned Q2 2030