The Beachfront Villas by Ellington

MajanEllington

The Beachfront Villas by Ellington is an off-plan project by Ellington in Majan, with 21 homes on 4 floors. DLD’s last inspection, on 26 Oct 2026, found it 35% built.

Built
35%
Handover
Q3 2026
Sales in 12 months
3
Homes
21

Progress

35%built
  1. Q4 2023Building started
  2. Q3 2026Planned handover · passed
  3. Oct 2026Last inspection · 35%
2 months past the planned date

Prices

Typical price by size

Typical price by size · Nov 2025 – Oct 2026
SizeTypical priceAED/sq ftSales
4+ bedsAED 19.16M8,111 sq ft2,9493

Latest sales

Newest first
3 off-plan sales · Nov 2025 – Oct 2026 · newest first
DateSizeSq ftAED/sq ftPrice
Feb 2026 · 1 sale
13 Feb 20264+ beds6,4972,949AED 19.16M
Dec 2025 · 2 sales
30 Dec 20254+ beds8,1112,279AED 18.48M
10 Dec 20254+ beds8,3484,507AED 37.62M

Location

Drive times

  • Downtown Dubai30min
  • Dubai Airport (DXB)27min
  • Dubai Marina32min

By car. Jumeirah Open Beach, the nearest beach, is 13.9 km away.

Rated schools

  • Repton SchoolUK/IB (Y 13) · Outstanding3.6 kmaway
  • GEMS Wellington Academy -FzeUK · Very good4.2 kmaway

Getting around

  • Nad Al ShebaGold Line · opens 20323.6 kmaway
  • MeydanEtihad Rail · planned5.5 kmaway
  • CreekGreen Line9.9 kmaway
  • Al JaddafHigh-speed rail · planned11 kmaway
  • Dubai InternationalDXB14 kmaway
Area guideMajanFinished homesAED 1,181/sq ft1-bed rentAED 65k/yrGross yieldEstimate6.6%

Developer

  • 18 finished
  • 25 being built, on time
  • 7 past their planned date
  • 1 not started
Escrow bank
Commercial Bank of Dubai
Legal name
Ellington Properties Development L.L.C

Also being built by Ellington

Ellington’s other projects
ProjectHandoverBuilt
The PortmanJVCQ3 2025Past planned date79%
UH West BY EllingtonJLTQ1 2026Past planned date71%
UH East BY EllingtonJLTQ1 2026Past planned date47%
The QuaysideBusiness BayQ1 2026Past planned date55%
The Waterside Villas BY EllingtonMajanQ2 2026Past planned date32%
All 51 Ellington projects
Questions

More questions about The Beachfront Villas by Ellington

Q3 2026, the planned date in DLD’s register.

No. It is 2 months past its planned date, and was 35% built at DLD’s last inspection on 26 Oct 2026.

Of Ellington’s 51 projects on DLD’s record, 18 are finished. Of the 32 being built, 7 are past their planned date.

In Majan, 30 minutes by car to Downtown Dubai and 27 to Dubai Airport (DXB). Creek Metro station on the Green Line is 9.9 km away.

More nearby

How the numbers work