Chavelle by Imtiaz
Bu KadraImtiaz
Chavelle by Imtiaz is an off-plan project by Imtiaz in Bu Kadra, with 139 homes on 19 floors. DLD’s last inspection, on 26 Oct 2026, found it 0% built.
- Built
- 0%
- Handover
- Q1 2029
- Sales in 12 months
- No sales
- Homes
- 139
Progress
- Q1 2026Building started
- Oct 2026Last inspection · 0%
- Q1 2029Planned handover
Homes
139 homes by size
- 1 bed65%91 homes · 792–1,707 sq ft · 8 layouts
- 2 beds24%33 homes · 1,521–3,293 sq ft · 5 layouts
- 3 beds10%14 homes · 2,120–2,587 sq ft · 2 layouts
- 4 beds1%1 home · 4,456 sq ft · 1 layout
Location
Drive times
- Downtown Dubai22min
- Dubai Marina34min
By car. Mercato Beach, the nearest beach, is 8.7 km away.
Rated schools
- Hartland International School - FZUK · Very good2.3 kmaway
Getting around
- Nad Al ShebaGold Line · opens 20323.2 kmaway
- MeydanEtihad Rail · planned3.4 kmaway
- CreekGreen Line4.4 kmaway
- Al JaddafHigh-speed rail · planned5.0 kmaway
- Dubai InternationalDXB8.9 kmaway
Developer
- 10 finished
- 28 being built, on time
- 3 past their planned date
- Escrow bank
- Not on record
- Legal name
- Imtiaz Ghd Real Estate Development L.L.C
Also being built by Imtiaz
| Project | Handover | Built |
|---|---|---|
| Beach Walk Residences 3 BY ImtiazDubai Islands | Q2 2026Past planned date | 100% |
| Cove Edition Residence 1 By ImtiazDubai Land Residence Complex | Q3 2026Past planned date | 90% |
| Cove Edition Residence 2 By ImtiazDubai Land Residence Complex | Q4 2026Past planned date | 60% |
| Luxur Tower By ImtiazJVC | Q4 2026Being built | 90% |
| Beach Walk Grand By ImtiazDubai Islands | Q4 2026Being built | 68% |
More questions about Chavelle by Imtiaz
Q1 2029, the planned date in DLD’s register.
It is not past its planned date. It was 0% built at DLD’s last inspection on 26 Oct 2026, with handover planned in 2 years.
139 homes on 19 floors: 91 1-bed flats of 792–1,707 sq ft, 33 2-bed flats of 1,521–3,293 sq ft, 14 3-bed flats of 2,120–2,587 sq ft and 1 4+ bed of 4,456 sq ft.
About AED 110k a year for a 2-bed in Bu Kadra.
Of Imtiaz’s 41 projects on DLD’s record, 10 are finished. Of the 31 being built, 3 are past their planned date.
In Bu Kadra, 22 minutes by car to Downtown Dubai and 34 to Dubai Marina. Creek Metro station on the Green Line is 4.4 km away.
More nearby
Off-plan nearby
- Parkway by Prestige OneFrom AED 1.57M11% built · Planned Q1 2028
- The WinslowNo sales0% built · Planned Q1 2028
- Ayaan Heights IFrom AED 1.75M20% built · Planned Q1 2028
- Zen LagoonsNo sales0% built · Planned Q2 2029
- Future ResidenceFrom AED 1.42M0% built · Planned Q2 2027
- Future Avenue TowerNo sales0% built · Planned Q3 2028